Projects

Grange Road

Client

Higgins Partnerships

Location

Grange Road, Plaistow, London, E13

Duration

36 weeks

Completion Date

September 2023

Contract Value

£478k

Specified System / Manufacturer

Bauder

Roof Area

2,900 m²

Scope of Works & Project Description

The works at Grange Road comprised Bauder waterproofing and bituminous felts across approximately 2,900 m² of roof area on a residential development. The scope included installation of the waterproofing system together with a foldable free-standing handrail and designated walkway for future maintenance access. The completed installation provides robust, long-term roof protection.

Grange Road (2)